New Nuclear Policy-Planning Council
Costings for Direct Disposal of Spent Nuclear Fuel
Table 2a: Case by Case Calculation of Cost of (Vertical) Disposal of Spent Fuel (figures in billion yen)
|
Cost Headings
|
Soft Rock
|
Hard Rock
|
|
Case 1
|
Case 2
|
Case 3
|
Case 1
|
Case 2
|
|
2 fuel assemblies per canister, buried vertically
|
4 fuel assemblies per canister, buried vertically
|
2 fuel assemblies per canister, buried vertically at 2 sites
|
2 fuel assemblies per canister, buried vertically
|
2 fuel assemblies per canister, buried vertically at 2 sites
|
|
Technological Development
|
214.3
|
214.3
|
214.3
|
213.8
|
213.8
|
|
Survey and Site Acquisition
|
240.3
|
224.7
|
284.8
|
247.9
|
299.3
|
|
Design and Construction
|
3,499.1
|
2,500.8
|
4,054.6
|
1,556.2
|
2,192
|
|
Above Ground Facilities
Below Ground Facilities
Above Ground Equipment
Below Ground Equipment
Other
|
134.9
2,730.3
453.3
137.8
42.9
|
111.1
1,813.1
417.7
116.1
42.9
|
156.5
2,983.8
623.2
212.8
78.4
|
99.8
589.6
504.3
319.6
42.9
|
118.9
668.1
728.1
598.4
78.4
|
|
Operations
|
1,966.7
|
1,486.2
|
2,247.2
|
1,803.7
|
2,257.9
|
|
Closing and Dismantling
|
215.6
|
243
|
365.4
|
241.2
|
360
|
|
Monitoring
|
119
|
119
|
237.9
|
119
|
237.9
|
|
Project Management
|
1,176.2
|
979.9
|
1,653.4
|
919.4
|
1,469.7
|
|
Consumption Tax
|
333.1
|
257.9
|
405
|
227.6
|
312.8
|
|
Subtotal
|
7,800.4
|
6,025.9
|
9,462.8
|
5,328.7
|
7,343.5
|
|
Tax for handling of spent fuel materials etc.
|
761.6
|
761.6
|
761.6
|
761.6
|
761.6
|
|
Total
|
8,562
|
6,787.5
|
10,224.4
|
6,090.3
|
8,101.1
|
Table 2b: Supplementary Case by Case Calculation of Cost of (Horizontal) Disposal of Spent Fuel (figures in billion yen)
|
Cost Headings
|
Soft Rock
|
Hard Rock
|
|
Supplementary Case 1
|
Supplementary Case 2
|
Supplementary Case 1
|
|
2 fuel assemblies per canister, buried horizontally
|
4 fuel assemblies per canister, buried horizontally
|
2 fuel assemblies per canister, buried horizontally
|
|
Technological Development
|
214.3
|
214.3
|
213.8
|
|
Survey and Site Acquisition
|
199.6
|
224
|
244.6
|
|
Design and Construction
|
1,114.9
|
1,041.8
|
1,148.3
|
|
Above Ground Facilities
Below Ground Facilities
Above Ground Equipment
Below Ground Equipment
Other
|
74.9
325.9
435.8
235.4
42.9
|
73.3
320.9
407.1
197.6
42.9
|
73.8
120.7
486.3
424.6
42.9
|
|
Operations
|
1,385.8
|
1,150.5
|
1,555.9
|
|
Closing and Dismantling
|
201.7
|
203.8
|
219.3
|
|
Monitoring
|
119
|
119
|
119
|
|
Project Management
|
672.9
|
715.8
|
848.7
|
|
Consumption Tax
|
180.3
|
166.2
|
193.6
|
|
Subtotal
|
4,088.6
|
3,835.4
|
4,543
|
|
Tax for handling of spent fuel materials etc.
|
761.6
|
761.6
|
761.6
|
|
Total
|
4,850.2
|
4,597
|
5,304.6
|
Table 3: Area of Disposal Site and Cost of Disposal
| Area and Cost Headings |
Soft Rock
|
Hard Rock
|
|
2 fuel assemblies per canister,
buried vertically (2 sites)
|
2 fuel assemblies per canister,
buried vertically
|
| Area of disposal site (km2) |
18.8
|
11.5
|
| Total length of main shafts (km) |
88
|
43
|
| Total length of disposal shafts (km) |
290
|
216
|
| Total cost (billion yen) |
9,462.8
|
5,328.7
|
| Cost with 2% discount rate (billion yen) |
7,507.5
|
4,226.8
|
Unit cost with 2% discount rate
(million yen/ton) |
336
|
189
|
Table 4: Disposal Schedule
| Time of commencing disposal |
35 years after establishment of implementing organization
|
| Time of completing disposal |
100 years after commencing disposal
|
| Period for monitoring after completion |
300 years after closing disposal site
|
Table 5: Unit Cost of Management and Disposal (2% discount rate)
Total period of operation (units: million yen/ton)
| Cost Headings |
Reprocessing Case
|
Direct Disposal Case
|
| Transport of spent fuel to reprocessing plant |
18
|
-
|
| Reprocessing |
253
|
-
|
| Transport of spent fuel to interim storage facility |
16
|
16
|
| Interim storage |
54
|
54
|
| Storage of high level waste (HLW) |
24
|
-
|
| Transport of HLW |
3
|
-
|
| (Disposal of HLW) or direct disposal of spent fuel |
(0.12 yen/kWh)
|
189 - 336
|
| Management and storage of TRU waste |
25
|
-
|
| Diposal of TRU waste (by deep geological disposal) |
29
|
-
|
Diposal of TRU waste (by means other than deep
geological disposal) |
10
|
-
|
| Fabrication of MOX fuel |
259
|
-
|
| Decommissioning of reprocessing plant |
27
|
-
|
Table 6: Results of Calculation of Cost of Fuel Cycle (yen/kWh)
| Cost Headings |
Scenario 1 |
Scenario 2 |
Scenario 3 |
Scenario 4 |
| Front End |
Uranium fuel |
0.57
|
0.57
|
0.61
|
0.61
|
| MOX fuel |
0.07
|
0.05
|
-
|
0.00
|
| Back End |
Reprocessing |
0.63
|
0.42
|
-
|
0.16
|
| HLW storage, transport and disposal |
0.16
|
0.10
|
-
|
0.06
|
| TRU waste management, storage and disposal |
0.11
|
0.07
|
-
|
0.03
|
| Intermediate storage of spent fuel |
0.04
|
0.06
|
0.14
|
0.13
|
| Direct disposal of spent fuel |
-
|
0.12 - 0.21
|
0.19 - 0.32
|
0.09 - 0.16
|
| Total |
1.60
|
1.4 - 1.5
|
0.9 - 1.1
|
1.1 - 1.2
|
| Electricity generation cost |
5.20
|
5.0 - 5.1
|
4.5 - 4.7
|
4.7 - 4.8
|
Diagram 1: costs arising year by year for burial in hard rock

Diagram 2: costs arising year by year for burial in soft rock

Evaluation Criteria
Evaluation of four scenarios
Interim Report
Previously published costs of the back end of the nuclear fuel cycle