Year |
Date |
Facility |
Overview |
Report
Classification |
2011 |
April
1 |
Onagawa
1 |
Damage
to field system circuit of emergency diesel generator (A). |
Law |
|
April
7 |
Tomaru
1 & 2 |
As
the Hokkaido-Honshu HVDC link (600 MW) automatically shut down due to the
earthquake Off-shore of Miyagi Prefecture, reactor heat output was reduced.
Because of this, the axial direction neutron flux output deviation of Units 1
and 3 differed from the standard value and deviated from operational limits. |
|
|
April
7 |
Higasidori
1 |
The
Miyagi Prefecture off-shore earthquake caused a loss of external power source
and the plant deviated from operational limits. |
|
|
April
7 |
Onagawa
2 |
Startup
transformer heat radiator oil leak. |
|
|
April
7 |
Onagawa
3 |
Automatic
full open operation of the suction valve on the high pressure core spray
system pressure suppression chamber was not possible. |
|
|
April 12 |
Kashiwazaki-Kariwa
5 |
Reduction
in output due to lubricating oil filter changeover on the reactor coolant
recirculation system MG (motor and generator) set. |
|
|
May 2 |
Tsuruga
2 |
A
rise in the concentration of radioactivity in the primary coolant, which
appeared to be caused by radioactivity leaking from the fuel. The reactor was
shut down and an inspection confirmed that one fuel assembly was leaking. |
|
|
May 14 |
Hamaoka
5 |
A
rise in conductivity occurred, indicating that seawater had entered the main
condenser during the time the reactor was being shut down. Of the roughly
21,000 main condenser (A) SG tubes, in an area roughly 14 m wide and 70 cm
deep, 43 SG tubes were damaged and 2 deformed. The endgap of the
recirculation piping of the electrically driven water supply pump, which is
installed inside the main condenser (A) was severed and had fallen off. The
circulation water pump and the water supply pump stopped, but it is thought
that 10 tons or more of seawater flowed into the reactor core. |
|
|
May 17 |
Tomari
1 |
Fractures
(one 6 mm, one 9 mm long) found in two locations in welds on reactor vessel B
loop discharge nozzles. |
|
|
June 27 |
Shika
2 |
When
inspecting 25 hafnium flat tube control rods, no fractures were found on the
tie rods, but fractures were discovered on the welds of the handle and sheath
of one rod and on the guide rollers of 11 rods. |
|
|
July 7 |
Tokai
2 |
A
worker involved in removal and handling operations for the control rod drive
mechanism reactor coordinates 18-23 in the area in front of the pedestal in
the reactor containment was exposed to radioactivity exceeding the scheduled
dose (total of 3.30 mSv per day). |
|
|
July 22 |
Rokkasho
Reprocessing Plant |
Inability
to start up two safety steam system boilers in the pre-processing building. |
Law |
|
August 3 |
Onagawa
2 & 3 |
Fastening
bolts on the spent fuel storage racks in the spent fuel pool were found to
the loose. |
|
|
August 18 |
Takahama
4 |
Fractures
due to stress corrosion cracking were found on one SG tube high temperature
side tube plate in each of two (B and C) out of three steam generators. |
Law |
|
August 30 |
Ohi
2 |
Deviation
from operating limits due to fall in reading of a thermometer in the
containment vessel. |
|
|
August 30 |
Fukushima
Daini 2 |
Cessation
of the high pressure reactor core spray system component cooling seawater
system. |
Law |
|
September 6 |
Tomari
3 |
Deviation
from operating limits due to inoperable central control room emergency
circulation system. |
|
|
September 13 |
Tokai
Reprocessing Facility |
During
changeover work on external electricity access, the ventilation blower,
dissolution off-gas blower, shearing off-gas blower for the high-level
radioactive liquid waste storage tank in the separation and refining plant in
the facility ceased working, making it impossible to maintain negative
pressure inside the storage tank. |
Law |
|
September 13 |
Kashiwazaki-Kariwa
7 |
Detection
of radioactive iodine in sampling from main exhaust pipe. |
|
|
September 26 |
Tokai
2 |
Missing
inner part of main steam relief valve (D). |
|
|
September 27 |
Tsuruga
1 |
Seawater
leak from seawater return pipe on emergency diesel generator (A). |
|
|
October 4 |
Genkai
4 |
Automatic
shutdown of reactor due to reduction in degree of vacuum in condenser. Flaw
in the procedure manual for replacement of the torque switch for the steam
master valve on turbine equipment shaft seals. |
Law |
|
October 8 |
Kashiwazaki-Kariwa
7 |
When implementing operational
tests on each of the scram pilot valves, one out of the 103 scram pilot
valves (core position 58-31/54-11) did not function correctly. |
|
|
October 17 |
Fukusima
Daini 4 |
Unscheduled
exposure (1.58 mSv) during decontamination work in the
containment. |
|
|
October 19 |
Tsuruga
2 |
Internal
exposure (inhalation of Cobalt-60) by worker. Measurement by whole body
counter showed a reading of approximately 58,500 counts/sec. |
|
|
October 26 |
Tokai
2 |
Water
was found to be leaking from one location (core coordinates 30-51) of the
control rod drive mechanism housing flange in the lower part of the reactor
pressure vessel. |
|
|
October 28 |
Tokai
Reprocessing Facility |
Through-holes
due to corrosion were found in the external duct linked to the main exhaust
pipe leading from the separation and refining plant. |
Law |
|
November 4 |
Kashiwazaki-Kariwa
7 |
Defect
in a valve on an emergency diesel generator. |
|
|
November 17 |
Shika
1 |
Damage
found to a cable in the control panel of the diesel generator for the
high-pressure core spray system. |
|
|
November 28 |
Onagawa
3 |
Corrosion
found on discharge check valve of control rod drive water pump (B). |
|
|
December 1 |
Fukushima
Daiichi 1to 6 |
Wrongful
use of alarm pocket dosimeters by workers of contracted companies. |
|
|
December 1 |
Kashiwazaki-Kariwa
2 |
Shutdown
of high-pressure core spray system diesel generator during regular
inspection. |
|
|
December 7 |
Mihama
2 |
Manual
shutdown of reactor due to increase in A-pressurizer spray valve gland
leak-off flow rate. |
|
|
December 16 |
Genkai
3 |
Breakage
of C charging pump main shaft. |
Law |
2012 |
January 13 |
Tokai |
Fire
in cooling tower on rooftop of solidification treatment building. |
|
|
January 13 |
Onagawa
3 |
During implementation of
repacement work for new rotor blades on a low-pressure turbine (B), a fissure
was discovered on one location and damage on another location on the base of
one rotor blade on the 15th stage rotor blades. After a detailed inspection,
fissures were discovered on a further two rotor blades. |
|
|
January 16 |
Onagawa
3 |
Fractures found
on a steam turbine cylinder, shell plate and discharge outlet. |
|
|
January 19 |
Kashiwazaki-Kariwa
5 |
Trouble
occurred during a confirmation test on the movement of control rods during a
regular inspection when control rods (14-27) were supposed to be inserted one
notch from full withdrawal, but actually entered 11 notches. |
|
|
January 27 |
Shimane
2 |
Neutron
source range monitoring system inoperable. |
|
|
March 3 |
Tokai
2 |
A
water leak was found in the neighborhood of the weld on the residual heat
removal system (C) low-pressure core injection system injection valve
differential pressure detection pipe. |
|
|
March 27 |
Fukushima
Daini 3 & 4 |
Contamination
by radioactive substances confirmed in a non-controlled area of a service
building. |
Law |
|
March 29 |
Takahama
3 |
Fracture
due to stress corrosion cracking found in tube plate on high temperature side
of one SG tube in C-steam generator out of the three steam generators. |
Law |
|
March 30 |
Hamaoka
5 |
40
corroded pores were confirmed in the condensate tank lining material during
an inspection in connection with the influx of seawater into the condenser
system, which resulted in damage to the main condenser SG tubes on May 14,
2011 in the course of cold shutdown operations after the reactor had been
shut down. |
Law |