Year |
Date |
Facility |
Overview |
Report
Classification |
2012 |
April
3 |
Onagawa
1 |
Cessation
of operation of spent fuel pool water clean-up system pump. |
|
|
April
3 |
Higashidori
1 |
Equipment
abnormality alarm activated in the A system of the containment atmosphere
monitoring system (CAMS). |
|
|
April
4 |
Onagawa
1 |
Breakdown
of electrical motor of the emergency cooling service seawater pump (A).
Caused by the occurrence of an electrical short due to corrosion from
penetration of rainwater. |
Law |
|
May
17 |
Tomari
3 |
Water
leak from controlled area auxiliary building air exhaust duct. |
|
|
May
30 |
Kashiwazaki-Kariwa
5 |
When attempting to withdraw the
control rods one notch to confirm the movement of the control rod drive
mechanism after recovery of isolation of the hydraulic control unit, a
problem occurred when control rods in core position 58-31 withdrew three
notches. A full confirmation of the action of the control rod drive mechanism
was implemented. At this time, in the action confirmation test conducted on
June 12, a problem occurred when core position 02-31 control rods also
withdrew two notches when the command was given to withdraw one notch.
Abnormalities were found in the directional solenoid valve (valve 122). |
|
|
June
4 |
Kashiwazaki-Kariwa
1 |
Defect in a
residual heat removal system electrical valve. |
|
|
June
7 |
Onagawa
1 |
Damage
to the bearings on the reactor building overhead crane runway. |
Law |
|
June
15 |
Onagawa
2 & 3 |
As
a result of an inspection conducted on the upper part of the channel boxes
of fuel stored in the Unit 2 the spent
fuel pool, it was confirmed that of 1807, the clip joints on the upper part
of 13 channel boxes were partially damaged (max. length approximately 1.1
cm). Of the total of 1386 boxes in Unit 3, 19 were confirmed to have similar
damage. |
|
|
June
15 |
Genkai |
Burnout damage to lighting cable
in miscellaneous solids melting treatment building. |
|
|
July
4 |
Tokai
2 |
Fracture due to
stress corrosion cracking found in proximity to weld on one of four parts
fixed to a steam dryer in order to hoist it up. |
|
|
July
6 |
Tsuruga
2 |
Damage
found on water circulation piping. |
|
|
August
1 |
Kashiwazaki-Kariwa
7 |
Main
exhaust stack radiation monitor sampling pipe found to have a defective
connection. |
|
|
August
10 |
Tsuruga
1 & 2 |
As a result of an inspection
conducted on the upper part of the channel boxes in the spent fuel pools, 3
of the fuel channel boxes in Unit 1 had partially damaged or missing clip
joints. No damage was found in the Unit 2 channel boxes. |
|
|
September
6 |
Tokai
Reprocessing Facility |
Contamination
was found on the surface of radioactive liquid waste piping in a utility room
in the analytical laboratory. |
Law |
|
September
10 |
Mihama
3 |
Seawater
was found to be leaking from the air cooling tower of emergency diesel
generator B. |
|
|
September
10 |
Shimane
1 & 2 |
As
a result of an inspection conducted on the upper part (clip) of all 4381
channel boxes (798 in Unit 1, 2648 in Unit 2, and 872 in Unit 3) that were
loaded into the reactor core or were being stored in the spent fuel pools, it
was confirmed that there was damaged parts on the clip joints of 13 channel
boxes (10 in Unit 1, 3 in Unit 2). |
|
|
September
25 |
Tomari
1 & 2 |
A
defect was found in the monitor data transfer of the discharge structure of
Units 1 & 2. A defect had occurred in the transmission of data in the
monitoring station. |
|
|
October
4 |
Kashiwazaki-Kariwa
5 |
Accident
involving inability to withdraw control rods (02-27) that occurred during a
control rod action test as part of a functional inspection of the control rod
drive hydraulic pressure system. |
|
|
October
10 |
Fukushima
Daiichi 5 |
Dropout
of the minimum flowrate bypass valve on the core spray system (B). |
|
|
October
16 |
Kashiwazaki-Kariwa
5 |
Deformation
of water rods in two fuel assemblies. |
|
|
October
26 |
Genkai
3 |
Reduction
in thickness of SG tubes in component cooling water heat exchanger B. |
|
|
November
3 |
Ikata
1 |
Defective
reading from neutron flux detector. |
|
|
November
3 |
Hamaoka
4 |
Of
72 rotor blades detached from the 12th stage of the generator side of the
low-pressure turbine (B), bending damage was discovered on the attachment
base (rotary blade side) on 4 of the blades, and fissures on the attachment
base (rotary blade side) on 11 of the blades. |
|
|
November
15 |
Onagawa
3 |
Foreign
object discovered on the lower part of the first spacer of a fuel assembly. |
|
|
November
24 |
Hamaoka
3 |
Fractures
found in the attachment base of rotary blades in the 12th stage of the
high-pressure turbine side and the 12th stage of the generating side of the
low pressure turbine (C). |
|
|
November
30 |
Tokai
2 |
Leakage
of waste cleaning liquid outside of a controlled area. |
Law |
|
December
3 |
Onagawa
1 |
Corrosion
on the second injection isolation valve in residual heat removal system A. |
|
|
December
12 |
Kashiwazaki-Kariwa
5 |
It
was confirmed that fuel rods inside the two fuel assemblies in which deformed
water rods had been discovered on October 16 had come into contact with each
other and that they did not possess the necessary function. |
Law |
|
December
17 |
Onagawa
1 |
A
fracture was discovered in the attachment base of the reactor cleaning fluid
pump (A) vane wheel. |
|
2013 |
January
4 |
Ningyo
Toge Environmental Engineering Center Refining and Conversion Facility |
Water
containing radioactive substances found to be leaking from an exhaust duct in
a non-controlled area. |
Law |
|
January
16 |
Fukushima
Daiichi 6 |
Leak
from seawater sampling line of the reactor closed cooling water system heat
exchanger (B). |
|
|
February
5 |
Mihama
1 |
Damage
to the turbine blade of emergency diesel generator A and bending damage to
weld between the turbine blade and shaft. |
Law |
|
February
6 |
Ohi
3 |
Divergence
from the operating limits of system B emergency direct current bus. |
|
|
February
16 |
Fukushima
Daiichi 5 & 6 |
Leak
in the intake chamber between the temporary tank storing retained water and
the (reverse osmosis membrane type) desalination apparatus. |
|
|
February
22 |
Fukushima
Daini 3 |
Damage
to the axis bearings of the reactor building overhead crane runway. |
|
|
March
14 |
Onagawa
1 |
Divergence
from operating limits due to automatic shutdown of emergency diesel generator
(A) (emergency diesel generator (B) being in shutdown for inspection). |
|
|
March
19 |
Kashiwazaki-Kariwa
1 |
Of
68 fuel assemblies that had completed tests, 6 were found with deformed water
rods, and of these it was confirmed that fuel rods had come into contact with
each other in one assembly, and did not possess the necessary function. |
Law |
|
March
22 |
Kashiwazaki-Kariwa
4 |
During
regular testing on the residual heat removal system (A), a problem occurred
when it was attempted to open one test flowrate adjustment valve (electrical
motor-operated valve) from the fully closed position, but the valve would not
open. |
|