Fukushima Now (27) Part 2, Current State of Post-Accident Operations at Fukushima Daiichi Nuclear Power Station (February to July 2024)

By Matsukubo Hajime   State of the Plant The water temperature in the containment vessels and the spent fuel pools (SFPs) shows no great variation despite seasonal temperature changes. The state of releases of...

CNIC Statement: Is there any point in the fuel debris sample collection at Fukushima Daiichi Nuclear Power Station Unit 2?

September 10, 2024 On September 10, 2024, Tokyo Electric Power Company Holdings (TEPCO) began collecting samples of the debris [1] at Unit 2 of the Fukushima Daiichi Nuclear Power Station. However, it is not...

Overview of Water Treatment Secondary Waste Issues at the Fukushima Daiichi Nuclear Power Plant

By Masano Atsuko   Work to clear up the mess from the accident at Fukushima Daiichi Nuclear Power Plant (below, Fukushima Daiichi) operated by Tokyo Electric Power Company Holdings, In. (below, TEPCO) has run...