Nuclear Reactors Planned or Under Construction (As at March 2010)
by
Citizens' Nuclear Information Center
·
Published September 4, 2010
· Updated February 27, 2015
2010 Nuclear Power Development Plan1
Power Company
Location
Power (MW)
Commence(d) Construction
Commence Operations
Status
Type
Tohoku Electric
Namie Odaka
825
FY2016
FY2021
BWR
Higashidoori-2*
1,385
FY2016 or after
FY2021 or after
ABWR
TEPCO
Fukushima I-7
1,380
April 2012
Oct. 2016
ABWR
Fukushima I-8
1,380
April 2012
Oct. 2017
ABWR
Higashidoori-1*
1,385
Dec. 2010
Mar. 2017
Safety Assessmemt
ABWR
Higashidoori-2*
1,385
FY2014 or after
FY2020 or after
ABWR
Chubu Electric
Hamaoka-6
around 1,400
FY2015
FY2020 or after
ABWR
Chugoku Electric
Shimane-3
1,373
Dec. 2005
Dec. 2011
Under Construction
ABWR
Kaminoseki-1
1,373
June 2012
March 2018
Safety Assessment
ABWR
Kaminoseki-2
1,373
FY2017
FY2022
ABWR
Kyushu Electric
Sendai-3
1,590
FY2013
FY2019
APWR
J-Power
Ohma
1,383
May 2008
Nov. 2014
Under Construction
ABWR
Japan Atomic Power Company
Tsuruga-3
1,538
Oct. 2010
March 2016
Safety Assessment
APWR
Tsuruga-4
1,538
Oct. 2010
March 2017
Safety Assessment
APWR
Total
14 Reactors
19,308
.
.
.
1. Table by CNIC (based on Electric Power Supply Plan for 2010 Fiscal Year (1 April 2009 – 30 March 2010), Agency for Natural Resources and Energy, March 2009). Last updated May 21, 2010.
*The Tohoku and TEPCO Higashidoori reactors are at different power plants. Both companies plan to build power plants in Hiagashidoori.