Power Company Location Power (MW) Commence(d) Construction Commence Operations Status Type
Tohoku Electric Higashidoori-2
1,385 TBD TBD ABWR
TEPCO
Higashidoori-1
1,385 Jan. 2011 TBD Under Construction ABWR
Higashidoori-2
1,385 TBD TBD ABWR
Chubu Electric Hamaoka-6 around 1,400 TBD TBD ABWR
Chugoku Electric Shimane-3 1,373 Dec. 2005 TBD Under Construction ABWR
Kaminoseki-1 1,373 June 2012 March 2018 Safety Assessment ABWR
Kaminoseki-2 1,373 FY2017 FY2022 ABWR
Kyushu Electric Sendai-3 1,590 TBD TBD APWR
J-Power Ohma 1,383 TBD TBD Under Construction ABWR
Japan Atomic Power Company Tsuruga-3 1,538 TBD TBD Safety Assessment APWR
Tsuruga-4 1,538 TBD TBD Safety Assessment APWR
Total 11 Reactors 16,003 . . .